Scenic Drive site 6 (Between Arataki and West Coast Rd.)

Works will start on the second site (scenic site 6) from 10 March 2025. This site has quite an extensive failure. It spans from the slope above the road to the slope below the road.

The design is for a concrete piled, tied-back wall.

We expect this will take at least 5 to 6 months to complete, depending on weather. We expect this repair to be completed in August 2025.

The slip repair works in May at Scenic 6 site near Arataki.